Vantage Successfully Delivered Shipment For Power Plant Project In Cote D’Ivoire – Africa

Energy

Vantage Successfully Delivered Shipment For Power Plant Project In Cote D’Ivoire – Africa

1  2  3  4  5
0/5 - 0 Bình chọn - 648 Xem

27/06/2022

Vantage Successfully Delivered Shipment For Power Plant Project In Cote D’Ivoire – Africa
 
Recently, Vantage Logistics' Projects Department continued to successfully transport a shipment of nearly 3,000 CBM to the Atinkou Combined-Cycle power plant in Cote D’Ivoire, Africa.

Project information:
- Project name: Atinkou Combined-Cycle Power plant in Cote D’Ivoire
- Commodity: silencer exhaust systems
- Volume: 20 packages, total volume of 190.4 tons ~ 3,000CBM, of which, the longest unit is 10.14mL x 5.15mW x 3.43mH – 14.3 tons, the widest unit is 7.96mL x 7.50mW x 364mH – 8.9 tons.
- Vantage’s scope of work:
+ Inland transport from the seller's mechanical workshop in Quang Ngai to the PTSC Dung Quat port yard.
+ Delivery from the yard in PTSC Dung Quat port to alongside the vessel.
- Shipment time: April – May 2022

Due to the nature of the shipment as high-value goods with oversized dimensions (11/20 packages with a width of over 7m), the utmost caution is required in the handling of the shipment. To do this, Vantage Project has arranged a team of deligation staff, engineers and field supervisors to closely monitor each stage in the shipment processing process since the factory until the goods arrive at the port and load onto the ship.

Besides, due to the effects of the prolonged epidemic situation, the project has been delayed many times. The parties had difficulties in finalizing the cargo storage plan becaus of the contract between the parties such as: storing goods at the factory's warehouse or at the port or at the yard outside the factory and the port... Vantage had actively offered a variety of solutions for client so that they can choose the most optimal plan that meets their needs.

At the same time, before the ship docks in Vietnam, it must dock at an Indonesian port, however, due to stormy weather and prolonged port jams, leaving Indonesian ports has become difficult and delayed many times before being officially docked at Dung Quat port. Vantage at this time has maximized its role in connecting the parties, monitoring the ship schedule every day extremely closely and regularly informing the parties so as not to delay the shipment's progress.