Vantage promptly finished re-exporting the shipment of shipping equipment for the Ea Nam Wind Power

Energy

Vantage promptly finished re-exporting the shipment of shipping equipment for the Ea Nam Wind Power

1  2  3  4  5
0/5 - 0 Bình chọn - 442 Xem

20/08/2022

Vantage promptly finished re-exporting the shipment of shipping equipment for the Ea Nam Wind Power Vantage Logistics' Project Department continued to promptly and safely finish the re-export the shipment of shipping equipment  for the Ea Nam Wind Power, at Trung Nam Wind Farm, Ea Nam, Ea H'Leo, Dak Lak Province, Vietnam.
Re-export of equipment on Container Flat rack (40'FR IG)

Project information:
  • Project name: Ea Nam Wind Power, Trung Nam Wind Farm
  • Commodity: re-export of equipment, parts that used for transportation of blade, nacelle from overseas to jobsite
  • Volume: ~300 teus
  • Scope of work:
+ Loading, safely lashing and securing, record and report
+ Deliver from jobsite to port of re-export destination
  • Period: Mar 2022 - now
Spare parts on Container Flat rack (40'FR OW)

Same as all other projects, Vantage Project Delegation also arrange sufficient personnel and optimized loading to minimize freight, safely and promptly.
Containers Bundle

The Ea Nam wind power project is currently the largest capacity wind power plant in the country, with fast construction and set up speed. Participating in logistics, an important part in the project, Vantage Logistics has achieved each jobs safely and promptly. 

 