Vantage Logistics Completes Handover of Oversized Equipment for the Quang Trach 1 Thermal Power Plant – A National Key Energy Project under the Quang Trach Power Centre, Quang Tri Province
25/11/2025
Vantage Logistics Completes Handover of Oversized Equipment for the Quang Trach 1 Thermal Power Plant – A National Key Energy Project under the Quang Trach Power Centre, Quang Tri Province

Project Highlights

Supporting National Key Energy Projects: Securing Timely Progress and Energy Security
The completion of the CSU handover in September 2025 ensures that the project’s equipment supply timeline is maintained, supporting PMB2 in executing several critical work packages. This reinforces Vantage Logistics’ position as a trusted logistics partner for large-scale energy developments.

Energy Development Context in North Central Viet Nam
The progress of the Quang Trach 1 project takes place as the North Central region undergoes significant structural changes:
Administrative Merger: From 1 July 2025, Quang Binh and Quang Tri officially merged to form the new Quang Tri Province, covering approximately 12,700 km² with a population of around 1.87 million. The region now possesses an expanded development corridor, including a 240-km coastline and a network of strategic multimodal logistics infrastructure (Hon La Port, My Thuy Port, Dong Hoi Airport, and Quang Tri Airport).
Large-Scale Clean Energy Orientation: The centre is not only home to Quang Trach 1 but also to several major projects driving the region’s energy transition:

Vantage Logistics – A Reliable Partner for Energy and Infrastructure Projects
Vantage Logistics continues to support energy and infrastructure developments by providing logistics solutions tailored for oversized equipment and technically demanding cargo. With experience gained from projects such as Quang Trach 1, Vantage remains committed to safe, timely, and cost-effective service delivery.




Go Back
Vantage Logistics has completed the handover of two Continuous Ship Unloader (CSU) systems and accessories moved from Shanghai, China to Hon La Port, Viet Nam.
This oversized shipment plays a crucial role in finalising a key component of the Quang Trach 1 Thermal Power Plant – a national strategic energy project currently under development at the Quang Trach Power Centre.
This oversized shipment plays a crucial role in finalising a key component of the Quang Trach 1 Thermal Power Plant – a national strategic energy project currently under development at the Quang Trach Power Centre.

Project Highlights
- Project name: Quang Trach 1 Thermal Power Plant
- Commodity: Continuous Ship Unloaders (CSU) and spare parts
- Volume: 2 UNITS / 2,739 TONS / 60,000 CBM
- Port of Loading (POL): Shanghai, China
- Port of Discharge (POD): Quang Trach, Viet Nam
- Timeframe: 09/2025

Supporting National Key Energy Projects: Securing Timely Progress and Energy Security
- Project: Quang Trach 1 Thermal Power Plant, part of Quang Trach Power Center
- Investor: Viet Nam Electricity (EVN)
- Project Management Unit: Power Project Management Board No.2 (PMB2)
- Location: Quang Trach Power Centre, Quang Dong Commune, Quang Trach District, Quang Tri Province
The completion of the CSU handover in September 2025 ensures that the project’s equipment supply timeline is maintained, supporting PMB2 in executing several critical work packages. This reinforces Vantage Logistics’ position as a trusted logistics partner for large-scale energy developments.

Energy Development Context in North Central Viet Nam
The progress of the Quang Trach 1 project takes place as the North Central region undergoes significant structural changes:
Administrative Merger: From 1 July 2025, Quang Binh and Quang Tri officially merged to form the new Quang Tri Province, covering approximately 12,700 km² with a population of around 1.87 million. The region now possesses an expanded development corridor, including a 240-km coastline and a network of strategic multimodal logistics infrastructure (Hon La Port, My Thuy Port, Dong Hoi Airport, and Quang Tri Airport).
Large-Scale Clean Energy Orientation: The centre is not only home to Quang Trach 1 but also to several major projects driving the region’s energy transition:
- Quang Trach II LNG Thermal Power Plant: Capacity 1,500 MW (2 × 750 MW), investment capital approx. VND 52,490 billion. The project is finalising its feasibility study and EPC contractor selection, with groundbreaking expected in Q4/2025 (December).
- Quang Trach III LNG Thermal Power Plant: Included in Power Development Plan VIII, located in Phu Trach Commune with a planned capacity of 1,500 MW. Investor selection (proposed as EVN) is underway for implementation during 2031–2035.
- Coal Import Port & Breakwater: Featuring two berths for vessels up to 100,000 DWT (coal throughput 7.2 million tonnes/year), ensuring stable fuel reception. This is also where the newly handed-over CSU systems will operate.
- 500 kV Quang Trach – Doc Soi Transmission Line: Successfully energised for technical testing. The double-circuit line spans more than 500 km, connecting the Quang Trach Power Centre to the national grid and ensuring stable transmission capacity.

Vantage Logistics – A Reliable Partner for Energy and Infrastructure Projects
Vantage Logistics continues to support energy and infrastructure developments by providing logistics solutions tailored for oversized equipment and technically demanding cargo. With experience gained from projects such as Quang Trach 1, Vantage remains committed to safe, timely, and cost-effective service delivery.
Contact Vantage Logistics to explore logistics solutions for energy projects.




Tags
Quang Trach 1 Thermal Power Plant Project Quang Trach II LNG fired Power Plant Quang Trach III LNG fired Power Plant Coal Import Terminal and Breakwater 500 kV Quang Trach Doc Soi Transmission Line Thermal Power Plant Project Continuous Ship Unloader CSU Spare Parts Equipment Materials Infrastructures Coal Unloading Equipment Hon La port Quang Tri Province Quang Binh Province Textile yarn Long An Qingdao China VantageLogistics VantageProject ProjectCargo Transportation OverWeight OverHeight OverLength OverWidth Oversized OOGCargo OutofGauge Machinery Equipment CargoHandling Trucking SeaFreight AirFreight FreightForwarder BreakBulk LCL FCL Container SuperCargo Oversea HeavyLift SteelStructure GeneralCargo