Temporary export of construction machinery for Atran Bridge Construction Project in Myanmar
14/01/2023
Temporary export of construction machinery for Atran Bridge Construction Project in Myanmar
[Vantage Logistics] Carrying out the temporary export of equipment for the Soil Cement Deep Mixing Works for the Atran Bridge Construction Project in Myanmar

Vantage has customs procedures for the temporary export of used construction machinery over 10 years. Sea freight for oversized cargo from FCA customer's port FCA to CIF Yang gon port, Myanmar.

Go Back
[Vantage Logistics] Carrying out the temporary export of equipment for the Soil Cement Deep Mixing Works for the Atran Bridge Construction Project in Myanmar


- Project information:
- Project: Soil Cement Deep Mixing Works for Atran Bridge Construction Project in Myanmar
- Commodity: Full set of pile driving RIG - Pile machine
- Volume:
- 3x 40'HC+ 1x 40'FR
- Maximum container size 7.00 mL* 3.30 mW* 3.30 mH* 27 tons - Shipment time: December – 2022

The cargo has been surveyed by Vantage for size and packed before proceeding to ensure the volume. Especially closely coordinate with the monitoring team at the scene to quickly solve arising problems. Ensure cargo arrives safely, fast, and cost-effectively.